Feasibility study embankment A7

Location

Linz, Austria

Completed

2024

Type

Concept

Client

ASFINAG Bau Management GmbH

A7, Asfinag concept study for elevated tracks with urb-x
A7, Asfinag concept study for elevated tracks with urb-x

Feasibility of an elevated cycle track using urb-x's system along the A7 motorway

Ahead of the planned A7 motorway rehabilitation south of Linz, Austria, ASFINAG evaluated options for a new cycling link running along the corridor. urb-x supported ASFINAG and the lead technical planner by developing and comparing 3D-modelled modular variants in a feasibility study.

The study applied an efficient urb-x hollow-box girder configuration designed for minimal impact on sensitive surroundings, including an adjacent protected nature reserve:

  • Structure: Straight hollow-box girders with alternating 15 m and 25 m spans

  • Deck: Steel deck with thin-layer reactive-resin surfacing

  • Drainage: Continuous 2.5% crossfall

Prefabrication enables fast installation with minimal site disruption. Additionally, the Gerber system allows column positions to shift longitudinally by up to 10% to navigate difficult ground, a crucial advantage when building alongside an active motorway and protected land.